Work continue on board Alye Parusa

08 July 2007

At the end of June we have received new Facnor furlers with new set of PBO inner cables. Facnor specialists had visited the boat in Falmouth and assembled the furlers, which now ready to go on the mast.

Currently Pendennis Shipyard is changing D1 chain plates. Since we have new PBO set of standing rigging lighter but significantly bigger in sizes – therefore boat designed Alex Simonis suggested to increase the size of D1 chain-plates with some hull main frame reinforcement.

Once new D1 are installed, the boat will be ready for mast step and tune by our rigging partner Allspars. 

 